π Understanding the Out-of-Sequence (OOS) Problem
Out-of-Sequence (OOS) progress is one of the most common yet critical scheduling issues in project management. It occurs when activities progress differently from their planned logical sequence, causing:
β Incorrect float calculations
β Misleading schedule forecasts
β Broken relationships between activities
β Unreliable critical path analysis
π Example: In a traditional Finish-to-Start (FS) relationship, a successor should not start before its predecessor finishes. However, in reality, execution may not follow this rule, leading to OOS dependencies.
π‘ Without proper handling, OOS can distort project analytics and affect decision-making.
π How Plannex Solves OOS Automatically!
Plannex’s Out-of-Sequence Solver is designed to detect, analyze, and fix OOS issues seamlessly. Hereβs how it works:
πΉ 1. Smart Detection of OOS Cases
β
Scans the entire schedule to identify out-of-sequence relationships
β
Supports all dependency types: FS, SS, FF, and SF
Β
πΉ 2. Automated Fixes for OOS Relationships
Plannex applies intelligent rules to correct each OOS scenario:
π Case 1: FS Violation
- Issue: Successor starts before predecessor finishes.
- Fix: Converts FS β FF (Finish-to-Finish) to match actual execution.
π Case 2: SS Violation
- Issue: Successor progresses while the predecessor is still not started.
- Fix: Converts SS β FF (Finish-to-Finish) for logical alignment.
π Case 3: FF Violation
- Issue: Successor finishes before its predecessor.
- Fix: Converts FF β SS (Start-to-Start) to maintain scheduling integrity.
π Case 4: SF Relationship Issues
- Issue: The successor completes before the predecessor even starts (rare but problematic).
- Fix: Removes the SF relationship to avoid incorrect logic.
πΉ 3. Detecting New Open-End Activities
π Fixing OOS relationships may create new open-end activities (tasks with no logical predecessors or successors).
β
Plannex automatically flags new open-end tasks so you can review and adjust dependencies before importing to Primavera P6.
πΉ 4. Tracking Changes with Comments
π Plannex doesnβt overwrite your schedule blindly!
β
All modifications are commented and logged in the original predecessor sheet (TASKPRED_old) for full traceability.
π Why Plannex?
β Fully automated OOS detection & correction β No manual fixes required!
β Prevents misleading float values & broken logic
β Identifies and tracks new open-end activities
β Provides a transparent modification history
β Saves time and improves schedule accuracy
π And the best part? Plannex OOS Solver is FREE for up to 5000 relationships!
π Download Plannex now and take control of your project schedules!
#Plannex #OOSFix #PrimaveraP6 #ProjectManagement #ConstructionScheduling
-