The Out-of-Sequence (OOS) Challenge in Project Scheduling – Solved with Plannex!

The Out-of-Sequence (OOS) Challenge in Project Scheduling – Solved with Plannex!

πŸ” Understanding the Out-of-Sequence (OOS) Problem

Out-of-Sequence (OOS) progress is one of the most common yet critical scheduling issues in project management. It occurs when activities progress differently from their planned logical sequence, causing:

❌ Incorrect float calculations
❌ Misleading schedule forecasts
❌ Broken relationships between activities
❌ Unreliable critical path analysis

πŸ“Œ Example: In a traditional Finish-to-Start (FS) relationship, a successor should not start before its predecessor finishes. However, in reality, execution may not follow this rule, leading to OOS dependencies.

πŸ’‘ Without proper handling, OOS can distort project analytics and affect decision-making.

πŸ›  How Plannex Solves OOS Automatically!

Plannex’s Out-of-Sequence Solver is designed to detect, analyze, and fix OOS issues seamlessly. Here’s how it works:

πŸ”Ή 1. Smart Detection of OOS Cases

βœ… Scans the entire schedule to identify out-of-sequence relationships
βœ… Supports all dependency types: FS, SS, FF, and SF

Β 

πŸ”Ή 2. Automated Fixes for OOS Relationships

Plannex applies intelligent rules to correct each OOS scenario:

πŸ“Œ Case 1: FS Violation

  • Issue: Successor starts before predecessor finishes.
  • Fix: Converts FS β†’ FF (Finish-to-Finish) to match actual execution.

πŸ“Œ Case 2: SS Violation

  • Issue: Successor progresses while the predecessor is still not started.
  • Fix: Converts SS β†’ FF (Finish-to-Finish) for logical alignment.

πŸ“Œ Case 3: FF Violation

  • Issue: Successor finishes before its predecessor.
  • Fix: Converts FF β†’ SS (Start-to-Start) to maintain scheduling integrity.

πŸ“Œ Case 4: SF Relationship Issues

  • Issue: The successor completes before the predecessor even starts (rare but problematic).
  • Fix: Removes the SF relationship to avoid incorrect logic.
Β 
Β 

πŸ”Ή 3. Detecting New Open-End Activities

πŸ“Œ Fixing OOS relationships may create new open-end activities (tasks with no logical predecessors or successors).
βœ… Plannex automatically flags new open-end tasks so you can review and adjust dependencies before importing to Primavera P6.

πŸ”Ή 4. Tracking Changes with Comments

πŸ“Œ Plannex doesn’t overwrite your schedule blindly!
βœ… All modifications are commented and logged in the original predecessor sheet (TASKPRED_old) for full traceability.

πŸš€ Why Plannex?

βœ” Fully automated OOS detection & correction – No manual fixes required!
βœ” Prevents misleading float values & broken logic
βœ” Identifies and tracks new open-end activities
βœ” Provides a transparent modification history
βœ” Saves time and improves schedule accuracy

πŸ“Œ And the best part? Plannex OOS Solver is FREE for up to 5000 relationships!

πŸ”— Download Plannex now and take control of your project schedules!

#Plannex #OOSFix #PrimaveraP6 #ProjectManagement #ConstructionScheduling

Leave a Reply

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter

Don't miss new updates on your email

Share This Post

More To Explore

Plannex Tool

How to use Plannex AI

Overview of Plannex AI Plannex AI is an advanced feature within the Plannex ecosystem, designed to bring intelligent insights and automation to your workflows. Leveraging